Saturday, August 13, 2011

13th Aug, A Closer Look

Looking through the hall way; CHB at level of floor, filling up to this level
From the great room, at the stair area facing out
The Master's Bedroom Area, inspection by Mylene

Monday, August 1, 2011

Aug 1, Placed columns and Moving Up

Rainy days for the past week. Look forward to some sunshine soon.



Wednesday, July 27, 2011

27th July, Second Week

Installing the columns and foundation and readying scaffolding for the second floor.

It rained on and off for the past two days. Site is quite muddy.


More lumber for scaffolding for the second floor.


Sunday, July 24, 2011

24th of July, Day 5


Got most of the steel bars for foundation and columns. Excavating the foundation as well. Got a site visit from our Supervising Engineer as well, some minor adjustments.


Monday, July 18, 2011

Day One!

Today is Monday, July 18, 2011. Establishing the lot perimeter, clearing the area, setting up temporary shack and bringing in organisation. Nice sunny day.

South East Corner
South West Corner